Tower Compressor Station

picture-003

Capital Cost:

$10MM (Compressor)
$13 MM (Pipeline)

The Mandate:

The objective of this project was to build a grass-roots compressor station in northeast British Columbia. The compressor station is used to boost the pressure of sour gas from surrounding well sites located in the Tower gas field. The compressed gas is dehydrated and then tied-in to a raw gas gathering pipeline at 16-28-081-17 W6M which transports the compressed dehydrated gas to the Taylor McMahon gas plant.

The Solution:

We designed and managed construction of a sour gas compressor station in BC at 09-28-81-17W6. This included a separator package, a 12MMSCFD compressor package, a 25MMSCFD dehy, water and condensate storage tanks, VRU, flare and KO drum, with associated electricals. In 2008, an additional compressor of similar capacity, along with a second inlet separator was installed.

Associated flow lines included 19 km of 6" pipeline with a major HDD river crossing of 1.5 km at Septimus Creek at a total cost of $6MM, including $1.15MM for the crossing. Also 14 km of 8" pipeline including two HDD river crossings of 1 km and 0.6 km at Kiskatinaw River and an unnamed creek at a total cost of $8MM, including $1.5MM for the crossings.

 

Rosevear Oil Battery

Rosevear-Oil-Battery-2

Capital Cost:

$2.6MM (Battery)
$1.1MM (Pipelines)

The Mandate:

Resulting from exploration success, the client was expanding operations and required a new 2000 BPD oil battery complete with gas conservation and compression.

The Solution:

A new battery was designed and constructed consisting of an inlet / group & test separator skid, treater, produced oil, recycle and water tankage, solution gas compressor, VRU, flare system, and related ancillary equipment. The facility handles:

  • Maximum battery oil rate of 1890 BPD
  • Maximum battery water rate of 110 BPD
  • The installed gathering system included two satellites, 16 km of 3” pipeline, 6 km of 4” pipeline and 16 km of 6” sales gas line
 

Farrell Creek Sweet Gas Production Facility

Farrell-Creek-Sweet

Capital Cost:

$10.5 MM

The Mandate:

The proposed gas plant will be used to process gas from a sweet Montney gas zone that will be developed in the same area as the proposed gas production facility. Sweet gas from the well sites will be wet metered and brought into the facility along with any production liquids for processing. The sweet gas will be compressed and processed through a dew-point control skid (either dehy or refrige) and then metered before discharging into an existing Spectra Energy sweet gas sales pipeline. The produced water will be injected into a disposal well and any hydrocarbon liquids will be trucked from site and sold at a nearby sales terminal

The Solution:

GRB constructed and commissioned a sweet gas production facility in the Farrell Creek area of NE British Columbia.  This grass roots sweet service facility consisted of the following installations:

  • Inlet riser area complete with pig receivers and common inlet header
  • 3 phase horizontal inlet separator sized for a capacity of 50 MMSCFD of gas
  • 2 stage reciprocating compressor with a capacity of 12.5 MMSCFD of gas with infrastructure in place to increase total compression capacity up to 50 MMSCFD of gas with the addition of three (3) compressors of similar size
  • Dehydration package for dew point control sized for a capacity of 25 MMSCFD of gas with infrastructure in place to increase dehydration capacity to 50 MMSCFD of gas with addition of one (1) similar sized unit
  • Sales gas meter station operated by Spectra with H2S analyzer, gas chromatograph, water cut analyzer and a sonic meter run with a capacity of 50 MMSCFD of gas. The ability to switch out the sonic meter run for a larger size  to increase the capacity to 100 MMSCFD of gas
  • Outlet riser with provisions for future pig launcher and 10" diameter pipeline to tie-in the production facility into a Spectra sales gas pipeline
  • Two (2) 400 barrel storage tank for free liquids
  • Site power provided by a 190 kW natural gas driven generator package
  • On site instruments work on instrument air to be provided by an on-lease instrument air compressor package
  • Multi-well gathering system c/w with wellsite metering and SCADA data transmission and control.
 

Suffield Compressor Station

Suffield-Compressor-Station

Capital Cost:

$7 MM

The Mandate:

The client was looking to optimize the compression at an existing station:

  • Better handling (avoid temperature and capacity issues) of lowering inlet pressure by changing from three stages of compression to four stages of compression
  • Replace older equipment to minimize future downtime and repair bills.

The Solution: 

GRB engineered and managed the installation of the following equipment:

  • One 3550 BHP, two stage reciprocating compressor package with a Cat G3612TA LE Driver, and an Ariel JGC/6 Compressor
  • Three-phase utility power brought into site by the local utility vendor
  • A transformer for hook-up of the three phase utility power
  • A new electrical building containing the MCC for the K8 package
  • Above ground piping and electrical cable trays
  • Additional yard fencing surrounding the new compressor
  • A sales trim cooler, with bypass, for use during the summer months
 

Grand Forks Oil Battery and Water Disposal Facility (1000 BOPD)

grand-forks

Capital Cost:

$1MM

The Mandate:

The client required a new facility for oil treating, water separation and disposal at an existing oil satellite.

The Solution:

GRB engineered and managed procurement and installation of the facility, including:

  • Modifications for fuel gas take-off and ESD valving to an existing inlet header and test separator package
  • 6' x 32' free water knock out, complete with a 1 million btu burner system, fuel gas scrubber and associated instrumentation
  • Design and installation of a water injection building capable of handling 5000 bpd of fluid at 1000 psi discharge pressure
  • Two tanks within the tank farm containment area - one 750 bbl water tank and one 400 Bbl emergency oil tank
  • New 480 Volt Motor Control Centre and PLC control panel, and working with TransAlta to increase power of the existing three-phase power transformer
 

SAGD – Pelican Lake Pilot

pelican-lake-pilot-sagd

Capital Cost:

$10.5 MM

The Mandate:

To put on production a single well pair SAGD (Steam Assisted Gravity Drainage) pilot project. 

The Solution:

GRB engineered and management procurement and installation of a 50 MMBTU SAGD Pilot capable of supplying 495 t/d CWE steam at 77% quality and at 9300 kPag.  

  • 60’ x 100’ self framing building
  • Portable water treatment building
  • 25 mmbtu OTSGs
  • 1500 bbl water tanks c/w 1 mmbtu fired burners
  • 400 bbl blowdown tank
  • 200 bbl regen waste tank
  • 24” steam separator
  • BFW / emulsion heat exchangers
  • BFW / blowdown heat exchangers
  • Tie-in 1 on-lease source water well and 1 off-lease source water well
  • Tie-in 1 on-lease disposal well
  • Tie-in 1 on-lease SAGD well pair
  • Tie-in fuel gas and produced emulsion into existing Pelican Lake Oil Gathering System
 

Hayter Oil Satellite - High Water Volume Separation – SCUD

hayter-2

Capital Cost:

$2.8 MM

The Mandate:

The client needed to install field based facilities for removal of bulk water from the oil emulsion produced in the Hayter field and to provide additional water injection facilities.

The Solution:

GRB engineered and managed procurement and construction of this project, which contained three major components:

  1. Installation of a SKUD water separator.

    The SKUD is a 54" diameter by 55' long pressure vessel of proprietary design operating in a flooded condition and designed to remove bulk water from the oil emulsion. Approx. 50% of the inlet water is withdrawn off the bottom of the vessel and has a water quality of better than 400 ppm oil in the water. The remaining oil emulsion (approximately 4% oil) exits the top of the vessel and is pipelined to the Hayter Battery for processing in the unused Free Water Knock-Out.
  2. Installation of two water injection pumps.

    The water removed at the SKUD site is directly injected through new electrically driven pumps to new water injection wells. The two injection pumps, 900 BHP each, are multi-stage horizontal centrifugal pumps. Power distribution and Motor Control Center equipment, as required by the pumps, was also installed.
  3. Installed new pipelines (8" and 12") and line loops (10" and 12") to and from the SKUD location to reduce pressure drops in the field and allow production rates to increase.
 

Caribou North Compressor Station Expansion

Caribou-North-Compressor

Capital Cost:

$6.4 MM

The Mandate:

The client needed to expand the existing Compressor Station facility. A high level risk assessment (HAZOP) of the existing facility was also required to assess the impact of the planned expansion.

The Solution:

GRB conducted a HAZOP review that included mechanical, electrical, instrumentation, operations, operability and reliability issues. GRB engineered and managed the following critical items as part of the expansion:

  • Installed two 3 stage sales compressors totalling 4450HP, for a station total of 32,500HP.
  • Second electrical motor control centre (MCC) building and equipment (including surveying and managing the additional lease space for these items)
  • Produce water dump valves tied into the aboveground vent knockout tank
  • Installed new gas detection head in all compressor buildings
  • Installed secondary emergency vent system with aboveground Purchased / installed new office/control room
  • Purchased / installed two new computer workstations with local area network (LAN)
 

Beiseker Compressor Station - Coal Bed Methane

Beiseker-Compressor-Station

Capital Cost:

$2.8 MM

The Mandate:

Build a Sweet Gas Compressor Station to process shallow natural gas and from field pressure to TCPL sales gas pressure and specification.

The Solution:

GRB engineered and managed the construction of the Gathering System. The new Compressor Station was designed for a sales Gas capacity of 25 mmscfd. The plant was designed with a provision for future expansion of up to two additional compressors for a total of four compressors.

  • Low pressure segment of the Station is designed to operate with suction pressures ranging from 14-70 kPa (2-10 psig)
  • High pressure segment of the Station is designed to operate with suction pressures ranging from 70-517 kPa (10-75 psig).
  • Discharge and Sales gas pressures range from 5515-6894 kPa (800-1000 psig).
  • Major equipment installed included:
  • Three 1478 HP Reciprocating Compressor Packages
  • One 36" Glycol Dehydration Package
  • One 400 BBL. double walled Water Storage Tank
  • One 50 bbl. U/G Vent KO Drum Package
  • One 10" x 40' Vent/Flare Stack
  • One Office / Control Building
  • Instrument air compressor with 100% standby and volume vessel