SAGD – Pelican Lake Pilot

pelican-lake-pilot-sagd

Capital Cost:

$10.5 MM

The Mandate:

To put on production a single well pair SAGD (Steam Assisted Gravity Drainage) pilot project. 

The Solution:

GRB engineered and management procurement and installation of a 50 MMBTU SAGD Pilot capable of supplying 495 t/d CWE steam at 77% quality and at 9300 kPag.  

  • 60’ x 100’ self framing building
  • Portable water treatment building
  • 25 mmbtu OTSGs
  • 1500 bbl water tanks c/w 1 mmbtu fired burners
  • 400 bbl blowdown tank
  • 200 bbl regen waste tank
  • 24” steam separator
  • BFW / emulsion heat exchangers
  • BFW / blowdown heat exchangers
  • Tie-in 1 on-lease source water well and 1 off-lease source water well
  • Tie-in 1 on-lease disposal well
  • Tie-in 1 on-lease SAGD well pair
  • Tie-in fuel gas and produced emulsion into existing Pelican Lake Oil Gathering System